New
The data enrty for the month of March,2025 is open and will be closed by 8-04-2025 11:59pm     |  Gati Shakti- All the infrastructure projects costing more than Rs. 150cr under sanction Gati Shakti Programme may Please be uploaded on OCMS portal


Useful Links

Visitor
my widget for counting

SANKALP SE SIDDHI

Programme Implementation Wing

Successful implementation of various projects and schemes constitutes one of the most significant conditions for development. Effective coordination judiciously matched with regular monitoring thus becomes an important element in ensuring their successful completion with improved efficiency at a greater speed and on a reduced cost.

Project Highlight's

  • --------- Quaterly Project Status As On Oct-Dec,2024-25 ---------
  • Total No. of Projects(reported): 1856 (Rs.150 cr. & above)
  • Total Original Cost : Rs. 28,01,563.54 crore
  • Total Anticipated Cost: Rs.33,98,635.89 crore
  • % Of Cost Over Run With Respect to Latest Sactioned Estimates : 9.21%
  • Total Cost Of the Completed Projects : Rs. 1,82,984 crore
  • --------- Flash Project Status As on February,2025 ---------
  • Total No. of Projects(reported)in May,2024: 1682 (Rs150 cr. & above)
  • Flash Report for February,2025
  • --------- Trends of Projects During the Last Five years ---------
  • Added VS Completed
  • Due for Commissioning VS Completed

Forthcoming Events